Transport-related development of day care centers “Mäusekiste” and “Sonnenstrahl” in Leipzig
The sewer and manhole construction work is almost complete.
In addition to the construction of a road surface made of asphalt concrete, the sidewalks are to be renewed with
concrete block paving.
Drainage channels made of granite paving are intended to loosen up the appearance of the functional traffic facilities in addition to
water drainage.
Free School Leipzig eV
Construction is currently underway in the outdoor areas of the “Freie Schule”.
Shaft infiltration and block trenches are being built for the construction of several retention systems in order to allow the rainwater that accumulates on the traffic areas to seep away with a time delay.
An entrance structure at basement level with stairs and ramps is to enable
disabled access to the canteen on level 0.